We were successful in obtaining an approval in the Land and Environment Court for a modification of the Rose Bay Marina.

The Marina (the two-armed marina in the left of the photo) was modified by permitting 3 of the 4 berths at the northern end of Arm B (the longer arm) to accommodate 37m long vessels (previously restricted to 30m vessels).

The Court found that there would be no material visual impact caused by the modification and rejected the Council’s argument that the previous approval represented a “line in the sand” beyond which no further modification should be permitted. Rose Bay Marina agreed to relinquish 3 swing moorings to offset any potential parking, traffic and ecological impacts arising from the modification.

Link to Judgment